PV
Planned Value
EV
Earned Value
AC
Actual Cost
SV
Schedule Variance
EV-PV
CV
Cost Variance
EV-AC
CPI
Cost Performance Index
EV/AC
SPI
Schedule Performance Index
EV/PV
EAC
1. Eastimate assumptions not valid
2. Current Variances are atypical
3. Current Variances are typical
Eastimate at Cost completion
1. AC+ETC
2. AC+BAC-EV
3. BAC/CPI or AC+{(BAC-EV)}/CPI}
ETC
Estimate To Complete
EAC-AC
% to complete Percentage to complete
(EV/BAC)X100
VAC
Variance at completion
BAC-EAC
TCPI Time to complete Performance Index
1. (Based on BAC)
2. (Based on EAC)
1. (BAC-EV)/(BAC-AC)
2. (BAC-EV)/(EAC-AC)