  1. Define the Project Management Process Groups
    • Initiating
    • Planning
    • Executing
    • Monitoring & Controlling
    • Closing
  2. Define the Knowledge Areas of the PMBOK
    • Project Integration Management
    • Project Scope Management
    • Project Time Management
    • Project Cost Management
    • Project Quality Management
    • Project Human Resource Management
    • Project Communications Management
    • Project Risk Management
    • Project Procurement Management
    • (9 Knowledge Areas in total)
  3. Which process group has the most processes?
    Planning
  4. Which process group usually represents the largest expenditure of time and resources?
    Executing
  5. Define the relationship between planning and executing processes
    Executing processes carry out what was planned
  6. Define the relationship between planning and monitoring & controlling processes
    Monitoring & Controlling processes ensure the plan is working. They take the results from executing processes and compare them to what was planned.
  7. List the 2 processes that reside in the Initiating process group
    • Develop Project Charter
    • Identify Stakeholders
  8. List the 20 processes that reside in the Planning process group
    • Develop Project Management Plan
    • Collect Requirements
    • Define Scope
    • Create WBS
    • Define Activities
    • Sequence Activities
    • Estimate Activity Resources
    • Estimate Activity Durations
    • Develop Schedule
    • Estimate Costs
    • Determine Budget
    • Plan Quality
    • Develop Human Resource Plan
    • Plan Communications
    • Plan Risk Management
    • Identify Risks
    • Perform Qualitative Risk Analysis
    • Perform Quantitative Risk Analysis
    • Plan Risk Responses
    • Plan Procurements
  9. List the 8 processes that reside in the Executing process group
    • Direct and Manage Project Execution
    • Perform Quality Assurance
    • Acquire Project Team
    • Develop Project Team
    • Manage Project Team
    • Distribute Information
    • Manage Stakeholder Expectations
    • Conduct Procurements
  10. List the 10 processes that reside in the Monitoring & Controlling process group
    • Monitor & Control Project Work
    • Perform Integrated Change Control
    • Verify Scope
    • Control Scope
    • Control Schedule
    • Control Costs
    • Perform Quality Control
    • Report Performance
    • Monitor and Control Risks
    • Administer Procurements
  11. List the 2 processes that reside in the Closing process group
    • Close Project or Phase
    • Close Procurements
  12. List the 6 processes that reside in the Project Integration Management Knowledge Area
    • Develop Project Charter
    • Develop Project Management Plan
    • Direct and Manage Project Execution
    • Monitor & Control Project Work
    • Perform Integrated Change Control
    • Close Project or Phase
  13. List the 5 processes that reside in the Project Scope Management Knowledge Area
    • Collect Requirements
    • Define Scope
    • Create WBS
    • Verify Scope
    • Control Scope
  14. List the 6 processes that reside in the Project Time Management Knowledge Area
    • Define Activities
    • Sequence Activities
    • Estimate Activity Resources
    • Estimate Activity Durations
    • Develop Schedule
    • Control Schedule
  15. List the 3 processes that reside in the Project Cost Management Knowledge Area
    • Estimate Costs
    • Determine Budget
    • Control Costs
  16. List the 3 processes that reside in the Project Quality Management Knowledge Area
    • Plan Quality
    • Perform Quality Assurance
    • Perform Quality Control
  17. List the 4 processes that reside in the Project Human Resource Management Knowledge Area
    • Develop Human Resource Plan
    • Acquire Project Team
    • Develop Project Team
    • Manage Project Team
  18. List the 5 processes that reside in the Project Communications Management Knowledge Area
    • Identify Stakeholders
    • Plan Communications
    • Distribute Information
    • Manage Stakeholder Expectations
    • Report Performance
  19. List the 6 processes that reside in the Project Risk Management Knowledge Area
    • Plan Risk Management
    • Identify Risks
    • Perform Qualitative Risk Analysis
    • Perform Quantitative Risk Analysis
    • Plan Risk Responses
    • Monitor and Control Risks
  20. List the 4 processes that reside in the Project Procurement Management Knowledge Area
    • Plan Procurements
    • Conduct Procurements
    • Administer Procurements
    • Close Procurements