PRINCE2 2009 - BUSINESS CASE CONTENTS.txt

  1. What is the information contained in the Business Case - Jack Nicholson Surfing
    • Business Options
    • Time Scales
    • Major Risks
    • Benefits
    • Dis-Benefits
    • Costs
    • Reasons
    • Investment Appraisal
    • Responsibilities
  2. Where would you find information that relates to the alignement of the project to the corporate strategy
    Business Case - Benefits
  3. Where would you find information that relates to the Mapped from Outputs and Outcomes
    Business Case - Benefits
  4. Where would you find information that relates Quantitive information (with Tolerance)
    Business Case - Benefits
  5. Where would you find information that relates to Measurable factors
    Business Case - Benefits
  6. Where would you find information that relates to Measurable factors for the project
    Business Case - Benefits
  7. Where would you find information that relates to the assignment of benefits?
    Business Case - Benefits
  8. As a general rule what can the Benefits in a Business Case relate to?
    Financial and non-financial
  9. During the running of the project where would you be expected to find information relating to the Maintenance of the project costs?
    Business Case -Investment Appraisal
  10. During the running of the project where would you be expected to find information relating to the development costs of the project?
    Business Case - Investment Appraisal
  11. During the running of the project where would you be expected to find information relating to the operational costs of the project?
    Business Case - Investment Appraisal
  12. Where would you find information that relates to the earliest finish date?
    Business Case - Timescales
  13. Where would you find information that relates to the period costs and benefits?
    Business Case - Timescales
  14. Where would you find information that relates to the expectation of when the benefits will be realised?
    Business Case - Timescales
  15. Where would you find information that relates to the earliest start date?
    Business Case - Timescales
  16. Where would you find information that relates to the period when costs will be incurred?
    Business Case - Timescales
  17. Where would you find the responsibilites in relation to the project and who would it usually contain?
    • PM
    • Executive
    • Project Support
    • Senior User
    • Project Assurance
    • Corporate or Programme
  18. Where would you find the aggregrate of risks in a summary
    Major Risks
  19. Give and example of Dis-Benefit
    Drop in productivity
  20. Where would you find information relating to funding and where?
    Business case - Costs
  21. Where would you find information relating to maintenance costs and where?
    Business case - Costs
  22. Where would you find information relating to operational costs and where?
    Business case - Costs
  23. Where would you expect to find information that relates to the financial and non-financial aspects of the project?
    Business Case - Benefits
  24. Where would you expect to find information that relates to how the project will have positive effect on corporate or programme?
    Business Case - Benefits
  25. Where would you expect to find information that relates to the measurable positive aspects of the project?
    Business Case - Benefits
  26. Where would you expect to find information that relates to the quantitive information in a project?
    Business Case - Benefits
  27. Where would you expect to find information that has been collated by mapping the outputs and Outcomes?
    Business Case - Benefits