Who is responsible for project quality?
the PM
An assignable cause or variance indicates that
there is a problem that is probably not just the result of random events and therefore needs to be corrected
Define Quality
1. The degree to which a set of inherent characteristics fulfill project requirements
2. Conformance to requirements/specs
3. Fitness for use
4. Prevention over inspection
5. Meeting mutually agreed needs and expectations
What is the best way to improve the reliability and maintainability of a product?
Good DESIGN practices
What are two major components of quality costs?
1. Cost of conformance
2. cost of non-conformance
Under what conditions is sampling most useful?
- when the population is large
- when the cost of inspection is high
- when destructive testing is required
- when you believe there are not many defects
Name four possible effects of poor quality
- Increased costs
- Decreased productivity
- Increased Risk
- Increased cost of monitoring
What is the purpose of quality function deployment?
To provide better product definition, i.e. more accurate engineering specifications
Author
cbass
ID
52084
Card Set
PMP - Quality Management review
Description
PMP - Quality Management review
Updated
2010-11-29T01:48:57Z
Show Answers
Home
Flashcards
Preview