Driven Pile Project Fuel Costs
$6.00 to $8.00 per m/h
-
Driven Pile Project Labor and Equipment Burn
- $105/hr - Labor
- $50/hr - Equipment
-
Driven Pile Project Other Direct Costs
10 to 20% of Labor Costs
-
Kaeding Development 10.75" dia x 0.250 Driven Pile Project
Installed 68,815.43 feet of pileĀ
Project Cost $3,142,030
Contract Value $3,752,707
- Project Cost = $3,142,030 / 68,815 ft = $45.66/ft
- Contract Value $3,752,707 / 68,815 ft = $54.54/ft
-
Frank Production 10.75" dia x 0.250 Driven Pile Project
Installed 25,701 feet of pile
Project Cost $1,725,067
Contract Value $1,895,808
- Project Cost = $1,725,067 / 25,701 ft = $67.12 /ft
- Contract Value = $ 1,895,808 / 25,701 ft = 73.76 /ft
|
|