A bid to place equipment IN SERVICE shall be placed with the Program Load Dispatcher/Outage Coordinator at least before the planned IN SERVICE or testing date
three (3) full working days
How many days are needed if the work is complex
5 or more full working days
True/False
If no bid has been placed and it becomes necessary, or is expedient, to place equipment IN SERVICE the day it is completed, the supervisor in charge of the work will contact the Senior Load Dispatcher for approval.
True
True/False
In the case of large projects (e.g Receiving Station bank upgrade), all pertinent information (e.g. ratings, restrictions, de-ratings, time tables, etc.) must be provided to the Program Load Dispatcher/Outage Coordinator at the time the bid is placed
True