OO-8

  1. A bid to place equipment IN SERVICE shall be placed with the Program Load Dispatcher/Outage Coordinator at least            before the planned IN SERVICE or testing date
    three (3) full working days
  2. How many days are needed if the work is complex
    5 or more full working days
  3. True/False

    If no bid has been placed and it becomes necessary, or is expedient, to place equipment IN SERVICE the day it is completed, the supervisor in charge of the work will contact the Senior Load Dispatcher for approval.
    True
  4. True/False

    In the case of large projects (e.g Receiving Station bank upgrade), all pertinent information (e.g. ratings, restrictions, de-ratings, time tables, etc.) must be provided to the Program Load Dispatcher/Outage Coordinator at the time the bid is placed
    True
Author
Benjammincash
ID
356046
Card Set
OO-8
Description
High-Voltage Equipment IN SERVICE and OUT OF SERVICE Procedures