Adv. Test #1

  1. Process of getting a CLEARANCE on an Air Blast CB
    DC control switch must be open (De-Couple)
  2. Motorized Disc
    Must open the safety switch
  3. Who's responsible for tagging
    Tagging OUT OF SERVIE equipment or circuits is the responsibility of the station or section to which the equipment has been declared OUT OF SERVICE
  4. When a single manual operating device operates more than one set of disconnects on 34.5kv circuit breaker connected to a bus, the circuit breaker will be considered part of the bus when the disconnects are opened for the purpose of providing a bus CLEARANCE
    6 pole gang operated
  5. Disconnects that are only capable of interrupting only the magnetizing current of the transformer
    Oil-Immersed
  6. Temporary signs that have preprinted instructions and markings used to restrict operation of a piece of equipment
    APTs
  7. A Work Authority requiring the specified circuit or equipment to be Disconnected or Isolated from specified sources of energy and remain so until the Clearance is released. A Clearance permits the performance of work specified when the Clearance was issued
    Clearance
  8. True/False

    If an Authorized person holds Adjoining CLEARANCES, he may have disconnects operated
    True
  9. Achieved by obtaining Two Adjoining CLEARANCEs, or a Boundary CLEARANCE, which isolates the equipment and/or circuit necessary for work to be performed
    Disc Overhaul
  10. True/False

    A Disc Overhaul would require a Work Authority on the Bus and a separate Work Authority on the circuit associated with said Disc
    True
  11. True/False

    After transferring cooler groups on banks, you don’t need to check if the cooler groups are working
    False
  12. A Work Authority issued by the Load Dispatcher or their Field Representatives that states the specified circuit, circuit component, or equipment is DISCONNECTED or ISOLATED from specific sources of energy
    Clearance
  13. Clearance in the Field, grounds shall only be applied at that station on orders from the Load Dispatcher when requested by
    • An Operator of another station holding a Clearance on a circuit
    • A Work Authority Holder with a Clearance on a circuit
    • An Electric Trouble Dispatcher holding a Clearance on a Feeder
  14. True/False

    Temporary Protective Grounds (TPGs) and Temporary Bonding Equipment shall only be installed after a Clearance or Diagnostic Test Authorization (DTA) is issued, or a Clearance has been established under a Switch, Work, and Restore....
    Earth end must be connected to the ground grid first
    True
  15. True/False

    When projecting a ground through a set of disc, the disc shall have the same tag number as the grounds
    True
  16. What conditions must be met before projecting grounds
    • Disc must be of latching and locking type
    • To Ground would be deemed hazardous
    • Done with the full knowledge and approval of each individual clearance e holder
    • With prior approval from LD and A/B Chief, APTs may be removed for the purpose of projecting grounds
  17. True/False

    In the interest of saving time during emergency situations, it may be necessary to limit a Type 1 inspection, even further, to include only that equipment that is directly involved in the emergency, and its solution
    True
  18. True/False

    On a 230kv Bus, a CLEARANCE is issued , then the ground is closed
    True
  19. What equipment/circuit/Work Authority does the LD generate tags for
    • - 4.8kV feeders (except as noted above)
    • - 34.5kV circuits into a Substation
    • - Transmission lines - Inter-utility Tie Lines
    • - Transformers with more than one area of jurisdiction
    • - OKs TO Work Hot with a Hold on 34.5kV circuits
    • - OKs TO Work Hot with a Hold on Transmission circuits
  20. True/False

    May go on Local to perform emergency switching w/o contacting the LD to avoid personal injury
    True
  21. True/False

    Applying portable grounds if possible and unusually hazardous is required after the CLEARACNE is issued and before work begins at circuits 7.5kv and below
    True
  22. Who cannot work in a station w/o an ESO
    • Building Repairers
    • Carpenters Gardeners
    • Maintenance Laborers
    • Painters
    • Plumbers
    • Non Power System personnel
  23. True/False

    Ear Protection must be worn within 20ft. of Air Blast CBs (noise hazard) indoors
    False
  24. True/False

    Racking in ground devices must be done by an operator
    True
  25. True/False

    While washing hot insulators and a fire appears, keep spraying until the fire is out
    True
  26. True/False

    Equipment that is out on a clearance and is missing parts, status is the same as other equipment out on a clearance
    True
  27. True/False

    □□□□CLEARANCE IN THE FIELD always gets a slash upon issuance
    True
  28. True/False

    The boxes of a □□□□CLEARANCE IN THE FIELD stamp are used to record the number of such Clearances in the field that exist simultaneously on the same circuit
    True
  29. True/False

    Work is to be done at DS-208 under a Primary CLEARANCE, LD will tell RS-I, DS-208 has a CLEARANCE in the Field on the line
    True
  30. MAD

    4.8kv 
    5kv 
    138kv 
    230kv
    • 2’1”/25”
    • 2’7”/31”
    • 4’4”/52”
    • 6’8”/80”
  31. Switch and Leave Policy does not apply to which Work Authority
    SWR
  32. Which work condition is allowed under a Switch and Leave

    Multiple Crews
    Test Relays and Trip CBs
    RTU work
    Aerial Work
    Man Lift
    None of the above
  33. Switch and Leave applies to
    • SSO
    • ESM
    • ESC
    • ECC
    • communicator
  34. True/False

    < 600v, employee cannot be assigned to work alone except when clearing trouble, responding to hazard, emergency situation, or when performing work not contacting energized conductors
    True
  35. True/False

    Prior approval of superintendent of crew required to project grounds
    False
  36. Who does not need an ESO
    • QEW
    • Authorized Person
  37. A Person that is authorized to receive Work Authorities on circuits and equipment from the Load Dispatcher or their Field Representatives
    Authorized Person
  38. True/False

    138/230Kv Bus ground switch can be opened for work without asking LD and substituted with portable grounds
    True
  39. True/False

    Line Patrol Mechanics can work on Pot Heads if already grounded and tagged without an operator present
    False
  40. True/False

    Issuing of an OK TO work hot on a circuit should not prevent issuing of a CLEARANCE except if OK TO conflicts/violates the CLEARANCE
    True
  41. What is discussed regarding limits and hazards
    Opens, electrical/physical hazards, nature of work performed, equipment/tools needed
  42. Who can work under Work Authorities and re-issued OKs TO
    Authorized Person
  43. True/False

    Cannot connect CBs to source load test under a CLEARANCE, only under an OK To
    True
  44. If a worker bids a Clearance on this type of CB and the bid does not specify that air be left in the receiver, what must the operator do
    • -The air tank supply valve must be closed and left closed.
    • -The DC control switch and low pressure alarm switch must be   opened and left open.
    • -The air tank must be completely drained of air by opening   and leaving open it’s drain valve.
    • -The air tank supply and drain valves must be properly tagged   to prevent further valve operation
  45. What are some of the risk/dangers of paralleling regulators one step of neutral.
    Excessive and dangerous circulating current will result which may cause equipment damage, personnel injury, or relay operation
Author
Benjammincash
ID
355973
Card Set
Adv. Test #1
Description
Updated