PC 400 Division

  1. WC 411
    T56 engine mounts, doors, and afterbody (wagon wheel)
  2. WC 41L
    T56 engine repair shop (ICRL C1)
  3. WC 412
    P-3 APU repair shop/test cell (ICRL C3)
  4. WC 414
    T56 engine module repair shop, *RGB*, Power section, Torque meter, *Turbine*
  5. WC 415
    F414 Can and un-can shop
  6. WC 41B
    CFM-56, preservation de-preservation, and PM's
  7. WC 430
    Prop repair work center (ICRL C-3)
  8. WC 431
    Prop control repair
  9. WC 451
    T56 engine test cell shop
  10. What is the process for shipping engines/props/components off station?
    • Work center generates shipping request
    • PC signs and takes to *RMU*
    • RMU notifies when it is ready for pick up
    • Logbook is placed with engine/prop/component
    • Call heavy truck driver for pickup, he will sign receipt and leave a copy
  11. What is the NRFI F414 Shipping process?
    • Once three NRFI F414 engines are received email F414 engine manager requesting BCM-1 authorization with the serial numbers
    • He will reply with chain email and message giving engine transfer TCN
    • AZ's prep logbooks, place with engine cans
    • RMU will call with shipping paperwork
    • Call heavy truck driver for pickup
  12. Over-the-wing gearbox change
    • Squadron contacts FST to verify gripe
    • *Wing will contact FRC to see if we can support*
    • Squadron orders RGB, Torque Meter, RGB mounts, and parts kit
    • Squadron removes required components from AC
    • Squadron brings engine and work request to FRC
    • 41L replaces RGB after WR is approved
    • WR signed off with all QA in-pros
    • Squadron Op-checks on AC
  13. Deckplate Reporting
    • Engine Transaction Report (ETR)
    • Entered when we receive or issue and engine, install or remove a linked module
    • Must be entered by the end of the next day
  14. MEI
    • (Major Engine Inspection)
    • Performed on engines received with over 40 flight hours. 39.99 and under are only inspected and run on test cell
  15. High time components
    • Props: 7,500 hours BCM-7, if at 7,000 hours and cannot repair then prop will get sent to *Pacific Propellers International* (PPI) for rework
    • T56 Mounts: RGB side mounts, Power section top and side mounts all have 5 year high time from date of install
  16. Suspense
    • Suspense is done by Ander in Rpool or Jill in CCS
    • Suspense items are: Torque Meter, RGB, Power section, turbine, F414, T56, T-700, CFM-56, props
    • The main purpose of us using suspense is for CVWP or CPRW-10 to be able to issue components to specific documents
  17. T56 engine receipt process
    • Must be inducted within 10 days or receipt
    • Acceptance, inventory, and borescope
    • T-56 AZ CTR will initiate MAFs
    • DOD T56 engine production supervisor Patty will determine whether engine is immediately put into repair cycle or preserved
  18. T56 Engine Efficiency
    • Passing engine efficiency is 98-108% (listed on corrective action)
    • Below 98 requires troubleshooting, above 108 WC 451 must comply with high efficiency checklist
    • Once checklist is completed if engine is still above 108% test cell run MAF will be signed off as HE and RFI
  19. RFI OF TUCA
    • (Turbine Unite Change Assembly)
    • If serial number of rotor changes, entire assembly SN chances
    • When PC signing off MAF contact Andrew with new SN to get added into suspense with old SN in remarks block
    • New SN change will also be annotated on corrective action
  20. FRCNW F414 Capability level
    X-1, only authorized to can and un-can
  21. What AC does the F414 go in?
    F18
  22. What AC does the CFM56 go in
    P8
  23. What AC does the T56 go in?
    P3
  24. FRCNW CFM56 Capability
    • X-1, only authorized preservation, 25d, 56d, 90d, 365d inspections.
    • Shipping CFM56 requires truck with *air ride suspension*
    • before engine is loaded driver must watch loading video and sign form
    • 20k forklift required for loading at air terminal
  25. Wing CANN procedures
    • Squadron contacts wing to acquire part via Memo
    • Wing will contact FRC to see if they can support
    • Forward PN and SN to Patty
    • FRC pulls part from shelf or off engine
    • Must check "I to O level" in Nalcomis
    • FRC WILL NOT move the part without Wing CANN memo
  26. F414 and PROP issuing process
    • CVWP or CPRW-10 contacts FRC and says which squadron needs item
    • We identify the SN and AZ's start transfer once item is placed on order
    • Component, Logbook, and logset will be swapped 1 for 1
    • Once 1 for 1's complete email Andrew in Rpool or Jill in CCS asking to issue correct Sn to document number
    • Once issued sign POD in Rpool and document closed out
    • If engine issue and receipt is done, AZ's will log transfer and acceptance ETR
    • We do not deal directly with the squadron until the wing clears us to issue the component
  27. Project codes
    • ZQ9 03 is used for all 400 components
    • BK1/BK0 is used for all 400 SE
  28. T56 engine manager
    Steve duffy
  29. F414 engine manager
    Terry Horgan
  30. What happens during winds 25 MPH or higher?
    Notify WC 451 to shut down due to the possibility of losing power while running an engine
  31. What happens during winds of 20 MPH or higher?
    Cannot operate outdoor crane to put engine or prop onto test stand with the EIRV
  32. What's special about the first engine run of each month?
    Base environmental must perform opacity check
  33. Who is the PPI military liason?
    Bob Holsworth
  34. How many people are required to install T56 on test cell?
    5
  35. How many people are required to install or remove a prop?
    3
  36. When signing off an RFI maf for a T56, what must be done?
    Complete the MEI and RFI checklists to verify all INPROs have been completed and place them in the folder
  37. What is the Test Club
    FRCNW owned test prop with a high time of 1000 hours
Author
someguyyeah
ID
355164
Card Set
PC 400 Division
Description
Updated