BRXB

  1. True/False

    OK TO stamps are always preceded by the entity receiving the work authority
    True
  2. True/False

    When there are adjoining clearances, the operator, and only the operator, may operate the disconnects that are the border between the two clearances
    True
  3. True/False

    There is no such thing as a secondary OK TO
    True
  4. What indicate the number of OK TO’s issued on a specific piece of equipment
    Slashes in the boxes of a primary OK TO stamp
  5. True/False

    In a gas company station a feeder can be supplied from the 4.8kV transfer bus unregulated and regulated
    and from the 4.8kV reactor bus unregulated
    True
  6. True/False

    For the □□□□ OK TO ____ stamp, the blank is filled in with the work performed
    True
  7. An employee that is certified to receive Work Authorities on circuit and equipment from the Load Dispatcher or their Field representative
    Authorized Person
  8. An Authorized Person can work on non-system equipment up to         and below
    300V
  9.              in an emergency situation can be minimalized to only the equipment involved in the emergency
    type 1 inspection
  10. An OK TO work hot on a 34.5kV line is under the              jurisdiction
    Load Dispatcher’s
  11.                   regulate voltage at the load center
    Regulators
  12. Proper                 improves equipment efficiency
    voltage
  13. Regulator               adjust the percent of regulation
    limit switches
  14.               measures the voltage and tells the regulator to make changes
    Contact Making Voltmeter
  15. True/False

    At 7.5kV and below portable grounds may not be applied under unusually hazardous or impossible conditions for a CLEARANCE
    True
  16. The most important reason for a Station Inspection
    To confirm the status of equipment and switching conditions
  17. How are regulators wired?
    Open delta
  18. True/False

    Voltage at the load center is the same as the power bank’s output voltage at a distributing station minus the line losses when the regulators are blocked on neutral
    True
  19. In regulators, the                  changes the polarity between the secondary and primary
    reversing switch
  20. In regulators, the time delay helps to reduce                
    hunting
  21. In regulators, the time delay helps to reduce                
    hunting
  22. Regulators are considered self-contained as demonstrated by the fact that ________ are shut off when the regulators are de-energized
    voltmeters
  23. True/False

    Local work authorities are issue on non-system equipment
    True
  24. True/False

    A CLEARANCE that is overheld or brought forward is treated the same as any other clearances
    True
  25. True/False

    The term “Out of Service” declares that a piece of equipment has been disconnected from all sources of energy
    False - specific sources of energy
Author
Benjammincash
ID
354740
Card Set
BRXB
Description
VB
Updated