What are three separate subsystems of the 3M system?
- 1. Planned maintenance system (PMS),
- 2. Maintenance data system (MDS),
- 3. Intermediate maintenance management system (IMMS).
-
What document contains a numerical listing of outstanding deficiencies for all work centers aboard ship?
Current Ships Maintenance Project (CSMP).
-
If a problem arises with a piece of equipment that cannot be repaired within thirty days, you must prepare a deferred action using what form?
OPNAV Form 4790/2K
-
If the problem with a piece of machinery is beyond ship's force repair capability what form must be filled out? OPNAV
OPNAV Form 4790/2K
-
Because of rapid changes in the 3-M system, you should refer to a current copy of what publication?
OPNAVINST 4790.4 Series.
-
PMS schedules are categorized in what manner?
Cycle, Quarterly and Weekly.
-
What schedule displays the planned maintenance requirements to be performed between major overhauls of the ship?
Cycle schedule.
-
Who signs and dates the PMS Cycle schedule?
Engineer Officer (Department Head).
-
Who updates the PMS Quarterly schedule weekly?
Division Officer.
-
How long are PMS Quarterly schedules maintained?
1 year.
-
Who fills out and posts the weekly PMS schedule?
Divisional work center supervisor.
-
Who signs the weekly PMS schedule?
Division Officer.
-
Who updates the PMS weekly schedule daily?
Divisional work center supervisor.
-
What form provides maintenance personnel with the means to report discrepancies and problems within the PMS system?
PMS Feedback report form 4790/7B.
-
Who receives the green copy of the PMS feedback report 4790/7B?
Originating work center.
-
Who receives and maintains the blue copy of the PMS feedback report?
3-M Coordinator.
-
Where is the blue copy of the PMS feedback report kept?
In the 3-M Coordinator's suspense file.
-
Who serializes the PMS feedback report?
3-M Coordinator.
-
Who receives the pink copy of the PMS feedback report?
TYCOM.
-
Urgent PMS feedback reports are sent via what?
Naval message.
-
The responsibility for development and overall policy governing management of the 3-M system is the responsibility of whom?
Chief of Naval Operations (CNO).
-
Who exercises overall responsibility for 3-M operation?
FLTCEVCs.
-
Who exercises primary responsibility for the effective operation and support of the Ship's 3-M system under their claimancy?
TYCOMs.
-
Who has the overall responsibility for ensuring ship maintenance is accomplished following 3-M system procedures and that the 3-M system functions effectively within the command?
The'Commanding Officer.
-
Who is the ship's 3-M system manager?
The Executive Officer.
-
The principal 3-M assistant to Executive Officer is whom?
3-M Coordinator.
-
When is the current ship's maintenance project (CSMP) verified and updated?
Monthly.
-
The acronym MDP stands for what?
Maintenance index page.
-
What does the acronym LOEP stand for?
What does the acronym LOEP stand for?
Provides a listing of the maintenance index pages and system equipment not requiring PMS assigned to each work center.
-
The acronym MDP stands for what?
Maintenance index page.
An index of a complete set of maintenance requirement cards applicable to a ship system, subsystem, or equipment.
-
What does an "A" in the test column of a MIP indicate?
Testing is to be performed by shore activity only.
-
What is the "other" column used for on a MTP?
Administrative use by FTSCLANT/FTSCPAC.
-
Mandatory related maintenance requirements on the MIP are indicated by what?
The symbol#.
-
Who approves the recopying of a Quarterly PMS schedule?
Division Officer.
-
On the PMS Quarterly schedule what is listed in the "Next Four Weeks" column?
All PMS requirements due in the next four weeks.
-
What is OPNAV 4790/L used for?
A supplemental form providing additional information such as drawings and listings used in conjunction with the 4790/2K.
-
What form is used to report completion of alterations, maintenance actions that resulted in a configuration change?
OPNAV 4790/CK.
-
What is located in block 3 of OPNAV 4790/2K?
Job sequence number.
-
Block 35 of OPNAV 4790/2K contains what information?
Remarks relating to the maintenance action.
-
A priority code of 1 in block 41 of OPNAV 4790/2K means what?
Mandatory.
-
The NAVSUP form 1250 is used onboard what type of ships?
Nonautomated.
-
What NAVSUP form is used on mechanized (automated) ships?
DD form 1348.
-
When a repair part is required and no NSN can be determined, the part must be ordered using what form?
NAVSUP form 1348-6.
-
Which form is used as a Ship submittal of Configuration Change?
OPNAV 4790/CK.
-
what form is designed to serve a dual purpose: as a custody record and an inventory control document?
NAVSUP form 306.
-
When is it mandatory to use NAVSUP form 306?
When dealing with controlled equipage.
-
Who is responsible for coordinating the QA training program?
Quality assurance officer.
-
When dealing with quality assurance, what does the acronym CWP mean?
Controlled work package.
-
What publication is used for all QA matters?
Joint Fleet Maintenance Manual, CEVCLANTFLT/CEVCPACFLTINST 4790.3 Series.
-
What is a Formal work package (FWP)?
Written instructions prepared IAW JFMM 4790.3 for use in production and repair, delineating all essential elements and guidance necessary to produce acceptable and reliable results.
-
A motor rewind would require what type of QA package?
Formal work package.
-
Who is responsible for directly supervising the preparation of a Formal Work Package?
The Leading Petty Officer (LPO) in charge of the equipment.
-
Who approves pen and ink changes to a Formal Work Package?
The LPO/WCS or Division Officer responsible for affected step.
-
How are pen and ink changes made to a Formal Work Package?
By drawing a single line through the portion to be changed and entering the necessary change adjacent to that portion.
-
Who does the craftsman notify if rework is required?
The LPO or WCS.
-
Who authorizes all rework steps in a Formal Work Package?
The responsible officer.
-
What is a Departure From Specifications (DFS)?
A lack of compliance with any authoritative document, plan, procedure, or instruction.
-
Who reviews a DFS for technical accuracy and signs the DFS?
The Engineer Officer.
-
DFSs are classified in what two groups?
Minor and major.
-
A major DFS requires approval from whom?
TYCOM or NAVSEA.
-
Who approves a minor DFS?
ISIC.
-
QA audits are conducted by the governing ISIC at what periodicity?
Annually.
-
What is the function of a vertical QA audit?
To determine if a specific job or task has been completed in accordance with the required specifications.
-
What is the function of a horizontal QA audit?
To review one specific area or part of an area to ensure compliance with the governing requirements.
-
What is the color of a QA non-nuclear ID/control tag?
Green tag with black lettering.
-
A QA controlled material rejection tag is what color?
Red tag with black lettering.
-
Who signs and dates the QA controlled material rejection tag?
Division Officer.
-
Who approves the QA controlled material rejection tag?
Quality assurance officer (QAO).
-
What form is used to report a DFS?
QA Form 12.
-
What QA form is used for testing and inspection?
QA Form 17.
|
|