Last Planner System

  1. Breaking down the LPS
    Project management = organizational project activity

    Production planning = breaking down the activity into smaller tasks
  2. 4 steps of commitment are?
    • request
    • commit
    • declare complete
    • declare satisfaction
  3. Production planning is the process of...
    ...taking the activities from the master schedule and breaking them into the actual tasks that various trades will perform in the field.
  4. What constraints are being assessed during the make-ready process in the LPS?
    RESOURCE
  5. Production planning
    allocates resources for day-to-day functions to complete project milestones.
  6. Who dictates the schedule in LPS?
    Foremen
  7. Make ready process aims to:
    • shape workflow sequence and rate
    • define constraints
    • match workflow and capacity
    • maintain a backlog of ready work
    • develop detailed plans for how work is to be done
    • address safety, environmental and quality issues
  8. Data lists and bar charts are helpful with what?
    To evaluate activities with repetitive tasks to ensure proper flow for the activities.
  9. Name 5 levels of LPS and a question that each must answer:
    • 1. master scheduling - feasibility, have confidence that the project is doable
    • 2. phase scheduling - develop a plan for reaching each milestone
    • 3. make-ready planning - remove constraints early
    • 4. weekly work planning - establishing what will be done from what can and should be done.
    • 5. daily huddles - getting on the same page and learning from what has been done.