Breaking down the LPS
Project management =
organizational project activity
Production planning =
breaking down the activity into smaller tasks
4 steps of commitment are?
request
commit
declare complete
declare satisfaction
Production planning is the process of...
...taking the activities from the
master schedule
and breaking them into the actual tasks that various trades will perform in the field.
What constraints are being assessed during the make-ready process in the LPS?
RESOURCE
Production planning
allocates resources for day-to-day functions to complete project milestones.
Who dictates the schedule in LPS?
Foremen
Make ready process aims to:
shape workflow sequence and rate
define constraints
match workflow and capacity
maintain a backlog of ready work
develop detailed plans for how work is to be done
address safety, environmental and quality issues
Data lists and bar charts are helpful with what?
To evaluate activities with repetitive tasks to ensure proper flow for the activities.
Name 5 levels of LPS and a question that each must answer:
1. master scheduling - feasibility, have confidence that the project is doable
2. phase scheduling - develop a plan for reaching each milestone
3. make-ready planning - remove constraints early
4. weekly work planning - establishing what will be done from what can and should be done.
5. daily huddles - getting on the same page and learning from what has been done.