  1. RBI is specifically targeted tot he application of RBI in what industries?
    Hydrocarbon and chemical process industry

    1.1
  2. This RP is intended to promote consistency and quality in identification, assessment, and management of risks pertaining to material deterioration that could lead to:
    Loss of containment

    1.2
  3. RBI is not a substitute for:
    Process hazards analysis (PHA) or hazard and operability assessment (HAZOP)

    1.3
  4. PHA Risk assessments typically focus on:
    Process unit design and operating practices and their adequacy given the unit's current or anticipated operating conditions.

    1.3
  5. RBI is also complementary to:
    Reliability centered maintenance (RCM) programs.

    1.3
  6. What equipment is covered by this RP?
    Pressure vessels, process piping, storage tanks, rotating equipment (Pressure-containing components), boilers and heaters, heat exchangers, and pressure-relief devices.

    1.4
  7. What equipment is not covered by this RP but may be covered by other processes such as RCM (Reliability centered maintenance)?
    Instrument and control, electrical, and structural systems, in addition to machinery components.

    1.5
  8. The primary audience for this RP is _____ and _______ personnel who are responsible for the mechanical integrity and operability of equipment covered by this RP.
    Inspection and engineering

    1.6
  9. RBI is not exclusively an ______ activity. RBI requires the involvement of various segments of the organization such as engineering, maintenance, and operations. Other stake holders should be familiar with the concepts and principles embodied by RBI to the extent necessary for them to understand the risk assessment process and to be able to accept the results.
    Inspection

    1.6
  10. What is API 581?
    Risk-Based Inspection Methodology

    2
  11. What is API 752?
    Management of Hazards Associated with Location of Process Plant Permanent Buildings

    2
  12. What is ASME PVRC Project 99-IP-01?
    A Comparison of Criteria for Acceptance of Risk

    2
  13. What is OSHA 29 Code of Federal Regulations (CFR) 1910.119?
    Process Safety Management of Highly Hazardous Chemicals