  1. Main Space Flood (MSF) Symptoms/Indications
    • 1. Bilge Alarm Actuates
    • 2. Space bilge level rising rapidly
    • 3. Inability to control bilge level by normal methods
  2. Main Space Flood (MSF) Possible Effects
    • 1. Loss of vital equipment/systems
    • 2. Machinery space(s) flooded
    • 3. Grounding of electrical equipment
  3. Main Space Flooding (MSF) Controlling Actions
    • CAUTION: IF FLOODING CANNOT BE CONTROLLED BY INSTALLED DRAINAGE OR RISES TO LEVELS ENDANGERING EQUIPMENT OR PERSONNEL, PROCEED TO IMMEDIATE ACTIONS
    • A. RCO order CRT man affected space
    • B. When ordered, CRT man affected space
    • C. CRT report to RCO "Manned & Ready"
    • D. CRT conduct primary investigation
    • E. CRT report source/location/est. GPM/level in bilge to RCO
    • F. RCO secure affected equipment/source
    • G. RCO order CRT secure/isolate affected equipment
    • H. When ordered, CRT secure/isolate affected equipment
    • I. RCO align main drain system to dewater affected space
    • J. When required, RCO start fire pump as needed to maintain firemain pressure
  4. Main Space Flooding (MSF) Immediate Action Cautions/Warnings
    • CAUTION: CLOSING HATCHES AND DOORS WILL RETARD FLOODING AND PREVENT PROGRESSIVE FLOODING
    • WARNING: ALL ELECTRICAL POWER TO AFFECTED SPACE SHOULD BE SECURED IMMEDIATELY IN ORDER TO PREVENT ELECTRICAL SHOCK AND POSSIBLE OVERLOADING OF ONLINE SSDG
  5. Main Space Flooding (MSF) Immediate Actions
    • A. When required, RCO order CRT to man affected space
    • B. When required, and when ordered, CRT man affected space
    • C. When required, CRT report to RCO "Manned & Ready"
    • D. RCO report to OOD "Uncontrollable flooding in ____. Isolating space, request all hands damage control be set"
    • E. DCO establish comms with RCO
    • F. When DCO reports manned & ready, RCO turn over control of DC efforts
    • NOTE: Isolation will be set per isolation lists in RPM IAW NSTM 555
    • G. RCO secure affected equipment in affected space
    • H. Repair electrician electrically isolate affected space
    • I. Repair electrician report "space electrically isolated"
    • J. When flooding becomes uncontrollable, CRT evacuate affected space. Repair party ensure all hatches and doors are shut
    • K. CRT report to DCO "Flooding uncontrollable. Space Evacuated"
  6. Class Charlie Fire in Switchboard (MCCFS) Symptoms & Indications
    • 1. Arcing and smoke coming from swbd
    • 2. Erratic meter indications
    • 3. Heat
  7. Class Charlie Fire in Switchboard (MCCFS) Possible Effects
    • 1. Damage to swbd
    • 2. Failure of ship's electrical power
    • 3. Burns to personnel
  8. Class Charlie Fire in Switchboard (MCCFS) Controlling Actions
    None
  9. Class Charlie Fire in Switchboard (MCCFS) Immediate Actions
    • A. RCO isolate affected swbd
    • B. RCO E stop affected SSDG. Ensure generator breaker opens
    • C. RCO order CRT/Repair E to man affected space
    • D. When ordered, CRT/Repair E man affected space and man firefighting equipment
    • E. CRT/Repair E report to RCO "Manned & Ready & FF Equipment Manned"
    • NOTE: Isolation will be set as per isolation lists in RPM IAW NSTM 555
    • F. RCO order repair electrician to electrically isolate affected swbd
    • G. When ordered, repair E electrically isolate affected swbd
    • H. Repair E report to RCO "no_ swbd electrically isolated"
    • I. RCO ensure standby SSDG starts
    • J. RCO parallel standby SSDG to bus
    • K. RCO report to OOD "Class C fire in No_ Swbd; No_SSDG stopped. Electrical plant configuration is ____"