What planning step comes before “Create network diagram”?
Create activity list
-
What planning step comes before “Prepare procurement documents”?
Go back-iterations
-
What planning step comes before “Create project scope statement”?
Finalize requirements
-
What planning step comes before “Create WBS and WBS dictionary”?
Determine team
-
What planning step comes before “Determine critical path”?
Estimate time and cost
-
What planning step comes before “Develop budget”?
Develop schedule
-
What planning step comes before “Estimate time and cost”?
Estimate resource requirements
-
What planning step comes before “Gain formal approval of the plan”?
Develop final project management plan and a performance measurement baseline that are realistic
-
What planning step comes before “Hold kickoff meeting”?
Gain formal approval of the plan
-
What planning step comes before “Determine quality standards, processes, and metrics”?
Develop budget
-
What planning step comes before “Determine what to purchase”?
Create project scope statement
-
What planning step comes before “Plan communications”?
Determine all roles and responsibilities
-
What planning step comes before “Go back-iterations”?
Perform risk identification, qualitative and quantitative risk analysis, and risk response planning
-
What planning step comes before “Create process improvement plan”?
Determine quality standards, processes, and metrics
-
What planning step comes before “Determine all roles and responsibilities”?
Create process improvement plan
-
What planning step comes before “Perform risk identification, qualitative and quantitative risk analysis, and risk response planning”?
Plan communications
-
What planning step comes before “Estimate resource requirements”?
Create network diagram
-
What planning step comes before “Create activity list”?
Create WBS and WBS dictionary
|
|