What document lists stakeholders and relevant details for each?
STakeholder Register
What outlines strategies for managing various stakeholders expectations/involvement?
Stakeholder Management Plan
What tracks disagreements and/or unresolved matters and outlines plan for resolving?
Issues Log
What shows all changes made during a project along with their impact on various constraints?
Change Log
What are ways of predicting/assessing potential outcomes in light of various project variables?
Analytical Techiniques
What are the 4 Processes for Project Stakeholder Management and what process group are they in?
1. Identify Stakeholders - Initiating
2. Plan Stakeholder Managementt - Planning
3. Manage Stakeholder Engagement - Executing
4. Control Stakeholder Engagement - Monitoring & Control
What are the 4 inputs for the Identify Stakeholders Process?
1. Project Charter
2. Procurement documents
3. Enterprise environmental factors
4. Organizational process assets
What are the 3 tools/Techniques for the Identify Stakeholders Process?
1. Stakeholder analysis
2. Expert judgment
3. Meetings
What is the output for the Identify Stakeholders Process?
1. Stakeholder Register
What are the 4 inputs for the Plan Stakeholder Management Process?
1. Project Mgmt plan
2. Stakeholder register
3. Enterprise environmental factors
4. Organizational process assets
What are the 3 Tools/techniques for the Plan Stakeholder Management Process?
1. Expert judgement
2. Meetings
3. Analytical techniques
What are the 2 outputs for the Plan Stakeholder Management Process?
1. Stakeholder management Plan
2. Project documents updates
What are the 4 inputs to the Manage Stakeholder Engagement process?
1. Stakeholder Mgmt plan
2. Communications mgmt plan
3. Change log
4. Organizational process assets
What are the 3 tools/techniques for the Manage Stakeholder Engagement process?
1. Communication methods
2. Interpersonal skills
3. Management skills
What are the 5 outputs for the the Manage Stakeholder Engagement process?
1. Issue Log
2. Change requests
3. Project management plan updates
4. Project documents updates
5. Organizational process assets updates
What are the 4 inputs to the Control Stakeholder Engagement Process?
1. Project Management Plan
2. Issue Log
3. Work Performance Data
4. Project documents
What are the 3 tools/techniques for the Control Stakeholder Engagement Process?
1. Information management systems
2. Expert judgement
3. Meetings
What are the 5 outputs for the Control Stakeholder Engagement Process?
1. Work performance info
2. Change requests
3. Project mgmt plan updates
4. Project documents updates
5. Organizational process assets updates
Author
Anonymous
ID
228611
Card Set
PMP-Project Stakeholder Management
Description
PMP Stakeholder Management
Updated
2013-07-30T16:30:37Z
Show Answers
Home
Flashcards
Preview