What are the regulations important to design?
- 20 - RP
- 21 - Defect Reporting
- 50 - Reactor Licensing
- 51 - Environmental Licensing
- 71 - Transportation
- 73 - Physical Protection
- 100 - Site Criteria
-
What are the Apeendicies of 10 CFR 50?
- A - GDC
- B - QA
- E - E-plan
- G - Fracture Toughness
- H - Reactor Vessel Surveillance
- I - Offsite ALARA
- J - Containment Leakage Test
- R - Fire Protection
-
What are the elements of 10 CFR 50 Appendix A?
- General Design Criteria
- Definitions: LOCA, Single Failure, Aticipated Operational Occurances
- 1-5: Overall Requirements
- 10-19: Multiple Fission Produc Barriers
- 20-29: Protection and Reactivity Control
- 30-46: Fluid Systems
- 50-57: Reactor Containment
- 60-64: Fuel and Reactivity Control
-
Define LOCA
Postulated accident resulting from loss of reactor coolant at a rate greater than what the makeup system can replenish
-
Define Single Failure
multiple failures resulting from a single occurence which resuls in the loss of capability of a component to perform its intended safety function
-
Define Anticipated Operational Occurances
- conditions of normal operation which are expected to occur more than once during the life of the plant
- Examples: Loss of power to all reciculation pumps, tripping of the turbine generator set, Isolation of the main condenser, loss of all offsite power
-
Define Safety Related
- SSC's designed to remain functional to assure required safety function
- 1: Integrity of RCS boundary
- 2: Capability to shutdown the reactor and maintain safe shutdown
- 3: Capability to prevent or mitigate consequences of accidents which could result in offsite exposures
-
Explain 10 CFR 100.11
- Assume accidental fission product release - substantial metldown
- EAB
- LPZ
- PCD
- Multiple Reactor sites - Independence/Interconnection, Normal Releases Additive
-
Define EAB Criteria
- 0-2 Hour Accident Dose
- 25 Rem Whole Body
- 300 Rem Thyroid
-
DEfine LPZ Criteria
- 0-30 DayAccident Dose
- 25 Rem Whole Body
- 300 Rem Thyroid
-
Define PCD Criteria
> 1 - 1/3 times LPZ Distance
-
Explain 10 CFR 100.10
- Characteristics of Reactor Design
- Population Density
- Physical Characteristics of Site
-
Characteristics of Reactor Design from 10 CFR 100.10
- Radionuclide Inventory
- Form of Radioactivity
- Unique Features
- ESF Features
-
Physical Characteristics of Site from 10 CFR 100.10
- Seismic (App. A) (FSAR 2.5)
- Meteorologic (FSAR 2.3)
- Hyrologic (FSAR 2.4)
- Compensating Plant Safety Features
-
Elements of 10 CFR 100 Appendix A
- Safe Shutdown Earthquake (SSE)
- Operating Basis Earthquake (OBE)
- Fault / Surface Fault / Capable Fault
- Response Spectrum
- Soil Stability
- Seismic Instrumentation
- Design Basis Flood
-
Elements of 10 CFR 50 Appendix B, GDC 1
- 18 Total
- I. Organization
- II. QA Program
- III. Design Control
- IV. Procurement Document Control
- V. Instructions, Procedures, and Drawings
|
|