dependent demand
demand for items that are subassemblies or component parts to be used in the production of finished goods; derived from plans to make certain products such as w/ raw materials & parts used in producing a finished product; tends to be sporadic or lumpy= large quantities are used at specific points in time with little or no usage at other times
-
material requirements planning (MRP)
a computer-based info. system that translates mater schedule requirements for end items in time-phased requirements for subassemblies, components, & raw materials, working backward from the due date using lead times & other info. to determine when & how much to order; used for batch production
-
master schedule (or master production schedule)
1 of the 3 primary inputs in MRP; states which end items are to be produced, when these are needed, & in what quantities; quantities come from customer orders & forecasts
-
cumulative lead time (or stacked)
the sum of the lead times that sequential phases of a process require, from ordering of parts or raw materials to completion of final assembly; includes move & wait times in addition to setup and run times
-
bill of materials (BOM)
1 of the 3 primary inputs in MRP; a listing of all of the raw materials, parts, subassemblies, and assemblies needed to produce one unit of a product; each finished product has its own one of these
-
product structure tree
a visual depiction of the requirements in a bill of materials, where all components are listed by levels; hierarchical; shows the quantity of each item needed to complete one unit of its parent item
-
low-level coding
restructuring the bill of materials so that multiple occurences of a component all coincide with the lowest level at which the component occurs
-
inventory records
1 of the 3 primary inputs in MRP; includes info. on the status of each item by time periods, called time buckets; includes gross requirements, scheduled receipts, withdrawals, canceled orders, and expected amount on hand or on order
-
gross requirements
total expected demand for an item or raw material in a time period without regard to the amount on hand
-
schedule receipts
open orders scheduled to arrive from vendors or elsewhere in the pipeline; or works-in-progress
-
projected on hand
expected amount of inventory that will be on hand at the beginning of each time period; scheduled receipts + available inventory from last period
-
net requirements
the actual amount needed in each time period; the core of MRP processing; gross requirements - projected on hand inventory
-
planned-order receipts
quantity expected to be received by the beginning of the period in which it is shown
-
planned-order releases
planned amout to order in each time period; equals planned-order receipts offset by lead time; this amount generates gross requirements at the next level
-
pegging
the process of identifying the parent items that have generated a given set of material requirements for an item; working the process for MRP in reverse; enables managers to determine which products will be affected if orders are late due to late deliveries, quality problems, or other problesm
-
planned orders
schedule indicating the amount and timing of future orders
-
order releases
authorization for the execution of planned orders
-
changes
revisions of due dates or order quantities, or cancellations of orders to planned orders
-
performance-control reports
evaluation of system operation, including deviations from plans (missed deliveries and stockouts) and cost information
-
planning reports
data useful for assessing future material requirements; includes purchase commitments
-
exception reports
data on any major discrepancies encountered, such as late and overdue orders, excessive scrap rates, reporting errors, and requirements for nonexistent parts
-
backflushing
exploding an end items bill of materials (BOM) to determine the quantities of the components that were used to make the item; eliminates the need to collect detailed usage info. on the production floor
-
manufacturing resources planning (MRP II)
expanded approach to production resource planning, involving other areas of a firm (such as mktg & finance) in the planning process & enabling capacity requirements planning; have capability of performing simulation to answer a variety of "what if" questions so managers can gain a better appreciation of available options & their consequences
-
Closed-Loop MRP
when MRP II systems began to include feedback loops, they were referred to as this; evaluates a proposed material plan relative to available capacity; if proposed plan not feasible, it must be revised; evaluation referred to as capacity requirements planning
-
capacity requirements planning
the process of determining short-range capacity requirements; inputs= planned-order releases for the MRP, current shop loading, routing info., & job time; key outputs= load reports for each work center
-
load reports
department or work center reports that compare known & expected future capacity requirements with projected capacity availability; shows expected resources requirements for jobs currently being worked on, planned orders, and expected orders for the planning horizon
-
enterprise resource planning (ERP)
represents an expanded effort to integrate standardized record keeping that will permit info. sharing; financial, manufacturing, and human resources on a single computer system to manage it more effectively; composed of a collection of integrated modules= connects them
|
|