Defines a low level of WBS detail for immediate work to be accomplished while future work WBS is at a high level of decomposition untile it is soon to be started.
Schedule Management Plan
Decompose work packages into activities and milestones.
Establish the network diagram.
Determine the resources needed for the project.
Determine activity durations.
Integrate activity components into a schedule.
Deal with schedule changes and updates.
Dependencies
Manadatory
A constraint that MUST be completed before subsequent items can start.
Dependencies
Discretionary
A constraint that SHOULD be completed but is not absolutely required to be completed before subsequent items can start.
Dependencies
External
A constraint put in place by something external to the project team or organization.
GERT
Graphical Evaluation Review Technique. Uses feedback loops or multiple passes - usually a noise answer.
Lag
A delay between activities. Used where there is some type of constraint in which something must wait before it can continue. Example: time for paint to dry.
Lead
Accelerant of an activity. You use Lead when something can begin before its predecessor is totally complete.
Analogous (top-down) estimating method
Compare to previous project.
Can be create quickly but lacks detail such as individual piece estimates.
Bottom-Up estimating method
Individual itemas are estimated and summed up for the total.
Has detail and accuracy but can take a long time and the team could pad the estimate to compensate for unknowns.
Parametric estimating method.
Parameters around which the estimate is built. Cost per unit of work/material etc.
Can be done quickly and usually accurate
Computerized/Monte Carlo estimating method
Individual items are estimated, them summed for total cost.
Usually accurate and can include what-is scenerios. However ramp-up time and costs associated with setup can be high.
PERT
Program Evaluation Review Technique. Uses 3 estimates per activity:
P=Pessimistic, R=Realistic ("M" most likely) & O=Optimistic
PERT can be used to calculate time or cost.
PERT formula
(O + P + 4R) / 6
PERT Std Dev.
(P - O)/6
PERT Variance of an activity
((P - O)/6)**2
Three-Point Est
Uses a straight average (O + P + R)/3
Reserve Analysys/Estimate
Plans for unknowns or contingency.
Activity Lists
Contail all required activities, an identifier for each activity and detailed scope of work description for each activity.
Bar Chart
Representation of schedule activities that denote start and end dates and duration of each activity.
Network Diagram
Visual representation of network logic and scheduling, Typlically contain date info for critical path activites and are formatted as activity-on-node or logic bar chart
Critical Path & Slack
What is the critical path?
The longest path on the network diagram.
It has NO slack but can change as the project evolves.
There can be multiple critical paths.
It has the greatest project risk.
The project end date could be delayed if anything on the critical path has a problem.
What is "crashing"?
Usually involves putting more people/resources on critical path tasks.
What is "fast tracking"?
Analyzing the network diagram and sequencing of activities to accelerate the compleation of work by adjusting the sequence of tasks. Typically used to determine if some tasks can be started sooner. Can increase risk.